Ho Chi Minh City has handed over nearly 92% of the ground to implement the Ring Road 3 project Currently, localities in Ho Chi Minh City have handed over 91.7% of the ground to the investor to implement the Ring Road 3 project.
According to the Steering Committee of the Project Component 2 (compensation and resettlement support) of the belt project 3 in Ho Chi Minh City, as of July 14, localities have handed over 91.7% of the site (reaching 374 ha/ 410 ha).
Specifically, Hoc Mon District People’s Committee handed over 100% of the site, Cu Chi District People’s Committee handed over nearly 98% of the site (reaching 63/65 hectares), Binh Chanh district handed over more than 94% of the site (reaching 137/145 hectares). ) and Thu Duc City handed over more than 74% of the site (reaching 74/99 ha).
It is expected that by December 31 this year, localities will hand over 100% of the site to the investor to implement the project on schedule.
Recently, the People’s Committee of Ho Chi Minh City has asked the units to inventory, “ensure” the repair and handover progress of resettlement apartments for the 3rd belt project in Ho Chi Minh City.
Previously, the Compensation and Resettlement Steering Committee (the Steering Committee) had a meeting to discuss a number of problems related to compensation and resettlement support of the Ring 3 project.
On the basis of the report of the Department of Natural Resources and Environment and the discussion of the members attending the meeting, the Steering Committee agreed on the progress of repairing the resettlement apartment for the work of compensation, support, resettlement belt project 3.
For the resettlement apartment building in Vinh Loc B (Binh Chanh district), the People’s Committee of Ho Chi Minh City assigned the Department of Construction to report in detail the progress of repairing apartments in the resettlement apartment in Vinh Loc B.
The People’s Committee of Ho Chi Minh City requested the Department of Construction to specify the quantity, implementation plan, “commitment”, progress and completion time to hand over the resettlement apartments to households, “then” report to the Project Steering Committee on the success of the project. part 2, to update progress and take responsibility for implementation according to authority.
For the resettlement apartment building C8 in Man Thien Resettlement Area (Thu Duc City), the People’s Committee of Ho Chi Minh City assigned the People’s Committee of Thu Duc City to report the progress of the repair and sanitation of the surrounding environment and have a plan for implementation. .
The People’s Committee of Thu Duc City must commit to the progress and completion time to hand over the resettlement apartments to the households. At the same time, the locality reports to the Project Commanding Committee of component 2 to update progress and take responsibility for implementation.
The Ring Road 3 project in Ho Chi Minh City, the section through Ho Chi Minh City is more than 47 km long (through Thu Duc City, Binh Chanh District, Hoc Mon, Cu Chi) with a total investment of more than 41,000 billion VND (construction cost more than 22,400 billion VND and over VND 22,400 billion). more than 18,000 billion VND in compensation and ground clearance).
The project was started on June 18 last. According to the plan, the project will be basically completed in 2025 and put into operation from 2026.